Denison Reports 24% Phoenix Completion and C$161.1 Million in Spending
Denison Mines reported third-quarter results on November 4, 2026, estimating that its Phoenix in-situ recovery uranium mine was approximately 24% complete on September 30, 2026, after the first quarter of full-scale construction. Year-to-date project expenditures totaled C$161.1 million. The completion measure covers more than construction at the site. Engineering, project construction management and owner's costs were 32% complete, construction and construction indirect costs were 20%…