i-80 Gold to Proceed with Underground Program at McCoy-Cove


PR Newswire | Nov 22, 2021 06:01AM EST

11/22 05:00 CST

i-80 Gold to Proceed with Underground Program at McCoy-Cove RENO, Nev., Nov. 22, 2021

RENO, Nev., Nov. 22, 2021 /PRNewswire/ -i-80 GOLD CORP.(TSX: IAU) (OTCQX: IAUCF)("i-80", or the "Company")is pleased to announce it is proceeding with its planned underground, advanced-exploration program at the Company's 100%-owned McCoy-Cove Property ("McCoy-Cove" or "the Property") located in Nevada.

McCoy-Cove is one of four projects currently being advanced by i-80 and is one of the key projects contemplated in the Company's plans to restart the Lone Tree processing facility that includes an autoclave. The underground plan will include the construction of a decline and a level that will include multiple drill bays in order to upgrade resources and complete a Feasibility Study. The Cove deposit on the Property represents one of North America's higher grade gold deposits with grades in excess of 10 grams per tonne gold (g/t Au) (Table 1). See Premier Gold Mines press release dated January 18, 2021. The deposit remains open for expansion to the southeast.

Table 1 - McCoy Cove Resource

Mineral Resources

Tonnage Au Grade Ag Grade Gold Silver

(kt) (g/t) (g/t) (koz) (koz)

Indicated 1,007 10.9 29.1 351 943

Inferred 3,867 10.9 20.6 1,353 2,565

Mineral Resources have been estimated at a gold price of $1,500 per troyounce;

2. Mineral Resources have been estimated using gold metallurgical recoveriesof 79.5% and 85.2% for roasting and pressure oxidation respectively;

3. Mineral Resources have been estimated using a gold equivalent cutoff gradeof 0.141 opt;

4. One ounce of gold is equivalent to 98 ounces of silver;

5. The effective date of the Mineral Resource estimate is January 1, 2021;

6. Mineral Resources, which are not Mineral Reserves, do not have demonstratedeconomic viability. The estimate of Mineral Resources may be materiallyaffected by environmental, permitting, legal, title, socio-political,marketing, or other relevant factors;

7. An Inferred Mineral Resource is that part of a Mineral Resource for whichquantity and grade or quality are estimated on the basis of limited geologicalevidence and sampling. Geological evidence is sufficient to imply but notverify geological and grade or quality continuity. An Inferred MineralResource has a lower level of confidence than that applying to an IndicatedMineral Resource and must not be converted to a Mineral Reserve. It isreasonably expected that the majority of Inferred Mineral Resources could beupgraded to Indicated Mineral Resources with continued exploration; and

8. The reference point for mineral resources is in situ.

"McCoy-Cove is one of the four projects being advanced, with mineralization anticipated to be processed at the Company's recently acquired Lone Tree Complex", stated Matt Gili, President & COO of i-80. "With the processing arrangement we have with Nevada Gold Mines, in addition to our autoclave, we have secured the required processing that will allow us to build this high-grade mine that is an important component in our growth plans".

Formal Request for Proposal (RFP) documents were submitted to six underground mining contractors and site visits were completed in November. Contractor selection will take place in December 2021. i-80 is anticipating breaking ground for the underground plan at McCoy-Cove in early 2022.

The initial Scope of Work for the Cove Exploration Decline consists of a new portal and over 1,000 meters of underground development. From this decline and drill platform we will commence a 40,000 meter in-fill and definition drilling campaign, primary focused on upgrading the known resource.

The McCoy-Cove Property is strategically located approximately 50 km south of the Company's Lone Tree Complex, and immediately south of Nevada Gold Mines' Phoenix Mine within the Battle Mountain-Eureka Trend (Figure 1). The Property is accessed via an all-season road from Highway 55 in Nevada.

Qualified Person

The technical and scientific information contained in this press release has been reviewed by Tim George, PE, Manager, Engineering Services of the Company, and a is a Qualified Person within the meaning of National Instrument 43-101.

About i-80 Gold Corp.

i-80 Gold Corp. is a well-financed, Nevada-focused, mining company with a goal of achieving mid-tier gold producer status through the development of multiple deposits within the Company's advanced-stage property portfolio to complement existing gold production from the Ruby Hill open pit.

___________________________________

Certain statements in this release constitute "forward-looking statements" or"forward-looking information" within the meaning of applicable securities laws,including but not limited to, timing of the commencement and completion of theunderground plan work at the McCoy-Cove Property, the timing of completion of afeasibility study at the McCoy Cove Property, timing of commencement ofprocessing minerals from the McCoy Cove Property-. Such statements andinformation involve known and unknown risks, uncertainties and other factorsthat may cause the actual results, performance or achievements of the company,its projects, or industry results, to be materially different from any futureresults, performance or achievements expressed or implied by suchforward-looking statements or information. Such statements can be identified bythe use of words such as "may", "would", "could", "will", "intend", "expect","believe", "plan", "anticipate", "estimate", "scheduled", "forecast", "predict"and other similar terminology, or state that certain actions, events or results"may", "could", "would", "might" or "will" be taken, occur or be achieved.These statements reflect the Company's current expectations regarding futureevents, performance and results and speak only as of the date of this release.

Forward-looking statements and information involve significant risks anduncertainties, should not be read as guarantees of future performance orresults and will not necessarily be accurate indicators of whether or not suchresults will be achieved. A number of factors could cause actual results todiffer materially from the results discussed in the forward-looking statementsor information, including, but not limited to: material adverse changes,unexpected changes in laws, rules or regulations, or their enforcement byapplicable authorities; the failure of parties to contracts with the company toperform as agreed; social or labour unrest; changes in commodity prices; andthe failure of exploration programs or studies to deliver anticipated resultsor results that would justify and support continued exploration, studies,development or operations.

View original content to download multimedia: https://www.prnewswire.com/news-releases/i-80-gold-to-proceed-with-underground-program-at-mccoy-cove-301429691.html

SOURCE i-80 Gold Corp






Share
About
Pricing
Policies
Markets
API
Info
tz UTC-4
Connect with us
ChartExchange Email
ChartExchange on Discord
ChartExchange on X
ChartExchange on Reddit
ChartExchange on GitHub
ChartExchange on YouTube
© 2020 - 2026 ChartExchange LLC